NEW YORKโNASA delayed the planned Feb. 12 launch of the Space Shuttle Discovery by at least a week to allow extra time to evaluate vital fuel valves on the spacecraft.
Discovery was slated to deliver the last set of U.S.-built solar arrays to the international space station. The mission is now scheduled to blast off no earlier than Feb. 19 at about 4:41 a.m. EST, with an official launch target to be determined at a later date.
โBy looking at it right now, we think itโs about a week delay, but weโre not going to put pressure on the team,โ John Shannon, NASAโs space shuttle program manager, said in a Feb. 3 briefing at the agencyโs Kennedy Space Center in Florida. โWeโll just let the information drive us.โ
The delay is necessary to allow engineers time to be sure that pieces of Discoveryโs flow control valves will not chip off and damage vital plumbing between the spacecraftโs main engines and its 15-story external tank. The valves are used to keep the space shuttleโs hydrogen propellant tank pressurized as the orbiter rockets spaceward.
The valves were replaced on Discovery after engineers discovered damage to a similar valve that flew aboard its sister ship Endeavour last November.
During Endeavourโs Nov. 14 launch, a piece of one of three flow control valves chipped off, apparently from high-cycle fatigue, Shannon said. The valve functions much like a pop-up lawn sprinkler to funnel hydrogen gas from a shuttleโs main engine back into its external tank to maintain proper pressure levels, he added.
Shannon said the damaged valve on Endeavour caused no serious harm during that shuttleโs November launch and NASA officials want to be sure the same will be true for Discovery when it flies.
โWe donโt expect there to be a problem, but we donโt have the proof in hand,โ
Shannon said. โWe want to have that proof in hand before we commit to go fly.โ
Shuttle officials announced Discoveryโs flight delay Feb. 3 after a daylong meeting to discuss the orbiterโs launch readiness.
NASA engineers plan to perform a series of tests to evaluate what effects valve debris could cause during ascent. Top shuttle officials are expected to discuss the results from those tests the week of Feb. 9 before setting an official new launch target.
Michael Leinbach, NASAโs launch director, said his team of shuttle workers is currently in a holding pattern until a new launch date is set.
โOnce weโre given a launch date, weโll get back into our processing,โ Leinbach said.
Commanded by veteran astronaut Lee Archambault, Discoveryโs STS-119 mission will launch seven astronauts toward the space station to deliver the outpostโs last set of U.S. solar arrays. Four spacewalks are scheduled during the two-week spaceflight. The mission also will ferry Japanese astronaut Koichi Wakata to the space station, where he will replace NASA spaceflyer Sandra Magnus as a member of the outpostโs three-person crew.
Space station mission managers, meanwhile, are tackling several issues to prepare the outpost for Discoveryโs arrival this month and the planned shift to a larger, six-person crew later this year. They range from a recent vibration event associated with a Jan. 14 thruster firing to ongoing, but not insurmountable, glitches with new life-support equipment.
NASA space station program manager Mike Suffredini said he is confident the glitches will be resolved and the station will be ready to support the first six-person crew in late May as planned.
Suffredini said that while the vibrations on Jan. 14, which occurred during a routine Russian thruster firing to boost the space stationโs orbit, were stronger than the acceptable limits, they did not cause any structural damage to the outpost. During the two-minute, 22-second engine burn, the space stationโs current skipper Michael Fincke of NASA reported that the outpost shook more than heโd ever seen in his two increments aboard, but he did not hear creaks or groans from the structure, he added.
A video from a camera inside the station showed items shaking back and forth.
โYou can see things were moving around pretty good,โ Suffredini said.
But despite the shaking, the event did not impact the space stationโs 15-year design lifetime, he added.
On Feb. 3, space station managers in Russia and at NASAโs Mission Control in Houston canceled another thruster firing planned for the next day. The next maneuver may take place sometime in March, Suffredini said.
Discoveryโs STS-119 mission is NASAโs first of up to six planned shuttle flights for 2009. They include one final flight to overhaul the Hubble Space Telescope and a series of space station construction missions.